Fallon Road Overlay Fairview Road to City Limits
Project #300-6
Description: Install paving
fabric and tack oil with 1.5 inch asphalt concrete leveling course and 1.5 inch
asphalt concrete finish course with crown correction.

- Average Daily traffic: 2,515
- Estimated cost: $ 315,000
- Funding Source: STIP
- Start of construction: May 2003
- Completion: June 2003
- Supervisor District: 1

The existing road surface is multiple thin sections of asphalt with chip
seals. Due to increasing average daily traffic, subgrade failure is beginning to
appear. This roadway is a commuter connection from Fairview Road to State
Highway 156.
PROJECT
COMPLETE
|